File #: ID 22-266    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/31/2022 In control: City Council
On agenda: 2/17/2022 Final action: 2/17/2022
Title: Actions pertaining to the Veterans Boulevard Grade Separation Project (Council District 2): 1. ***RESOLUTION - 49th Amendment to the Annual Appropriation Resolution (AAR) No. 2021-178 appropriating $1,949,800 for the Veterans Boulevard Grade Separation Project (Requires 5 affirmative votes) (Subject to Mayor's veto) 2. Approve Contract Change Order No. 15 in the amount of $1,354,408 and an increase in contract time of one hundred sixteen (116) working days to Granite Construction Company, for the Veterans Boulevard Grade Separation, Project ID PW00683
Sponsors: Public Works Department
Attachments: 1. 22-266 Contract Change Order No. 15, 2. 22-266 49th Amendment to AAR No. 2021-178
REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

BRIAN KUJAWSKI, Senior Engineering Inspector
Public Works Department, Construction Management Division

SUBJECT
Title
Actions pertaining to the Veterans Boulevard Grade Separation Project (Council District 2):
1. ***RESOLUTION - 49th Amendment to the Annual Appropriation Resolution (AAR) No. 2021-178 appropriating $1,949,800 for the Veterans Boulevard Grade Separation Project (Requires 5 affirmative votes) (Subject to Mayor's veto)
2. Approve Contract Change Order No. 15 in the amount of $1,354,408 and an increase in contract time of one hundred sixteen (116) working days to Granite Construction Company, for the Veterans Boulevard Grade Separation, Project ID PW00683

Body
RECOMMENDATION

Staff recommends that City Council adopt the attached 49th Amendment to the Annual Appropriation Resolution (AAR) No. 2021-178 and approve Contract Change Order No. 15 with Granite Construction Company of Fresno, California (Granite) for a total increase in contract amount of $1,354,408 and an increase in contract time of one hundred sixteen (116) working days for the Veterans Boulevard Grade Separation Project.

EXECUTIVE SUMMARY

Staff recommends City Council approval of Contract Change Order No. 15 for the Veterans Boulevard Grade Separation Project to construct traffic signal safety lighting infrastructure and an asphalt pavement access road from existing Golden State Boulevard to the proposed realigned future of Golden State Boulevard for the purpose of providing temporary access to the newly constructed bridge crossing over the Union Pacific Railroad tracks and connecting to Bullard Extension/Riverside Drive.

City Council approval of Contract Order No. 15 provides vehicular access to Veterans Boulevard Grade Separation and allows the Contractor to reconstruct existing Carn...

Click here for full text