REPORT TO THE CITY COUNCIL


FROM: SCOTT L. MOZIER, PE, Director
Public Works Department

BY: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division

JESUS AVITIA, PE, Deputy City Engineer
Public Works Department, Engineering, Transportation Project Management

SUBJECT
Title
Approve a Preliminary Engineering Services Agreement, with BNSF Railway Company in the amount of $104,900 for the Quiet Zone Phase 3 Project (Council Districts 1 and 7)

Body
RECOMMENDATION

Staff recommends the City Council approve a Preliminary Engineering Services Agreement, with BNSF Railway Company in the amount of $104,900 for the Quiet Zone Phase 3 Project and authorize the Public Works Director or designee to execute the agreement and future amendments on behalf of the City of Fresno.

EXECUTIVE SUMMARY

The Quiet Zone Phase 3 Project will close the existing gap between North Fresno and Downtown Fresno by modifying and installing the required Supplementary Safety Measures required by the Federal Railroad Administration (FRA) to approve the proposed Quiet Zone between the Shields Avenue crossing and the Blackstone Avenue crossing. The project will analyze and design the improvements required at the five at-grade railroad crossings (Shields, Maroa, Clinton, McKinley, Blackstone), and will be coordinated with the Blackstone Avenue and McKinley Avenue BNSF Grade Separation Project and with the Shields Avenue Section 130 Safety Improvements Project. The proposed Preliminary Engineering Services Agreement (PEA) with BNSF in the amount of $104,900 will facilitate the design and construction support services necessary to complete the project. The roadway safety improvements in the project are funded with SB1 Road Maintenance and Rehabilitation Account (RMRA) funding.

BACKGROUND

The City has two existing Quiet Zones, with a gap between Shields Avenue and Blackstone Avenue. The Quiet Zone Phase 3 Project will close the existing Quiet Zone gap ...