File #: ID 23-259    Version: 1 Name:
Type: Action Item Status: Passed
File created: 2/1/2023 In control: City Council
On agenda: 3/9/2023 Final action: 3/9/2023
Title: Approve Contract Change Order No. 1 in the amount of $252,544.50 and extend the date of completion to April 11, 2023 for the Sewer Rehabilitation in the Area Bound by Blackstone, Maroa, McKinley, and Clinton Avenues Project ID RC00177 (Bid File 3836) (Council Districts 1 and 7).
Sponsors: Public Works Department, Department of Public Utilities
Attachments: 1. 23-259 Contract Change Order No. 01
REPORT TO THE CITY COUNCIL


FROM: BROCK D. BUCHE PE, PLS, Director
Public Utilities Department

SCOTT L. MOZIER, PE, Director
Public Works Department

BY: WILLIAM C. HERR, Assistant Director
Public Works Department, Construction Management Division

BRAD OBERG, Senior Engineering Inspector
Public Works Department, Construction Management Division


SUBJECT
Title
Approve Contract Change Order No. 1 in the amount of $252,544.50 and extend the date of completion to April 11, 2023 for the Sewer Rehabilitation in the Area Bound by Blackstone, Maroa, McKinley, and Clinton Avenues Project ID RC00177 (Bid File 3836) (Council Districts 1 and 7).

Body
RECOMMENDATIONS

Staff recommends that City Council approve Contract Change Order No. 1 with Emmett's Excavation, Inc., for a total increase in Contract amount of $252,544.50 and thirty (30) additional working days.

EXECUTIVE SUMMARY

On April 21, 2022, a Contract was awarded in the amount of $1,578,078.00 to Emmett's Excavation, Inc., for the Sewer Rehabilitation in the area bound by Blackstone, Maroa, McKinley and Clinton Avenues, utilizing the Cured In-place Pipe Process (CIPP). During the design engineer's review of the CCTV video, significant sections of sewer main were found to be unsuitable for CIPP rehabilitation and requires replacement by traditional trenching methods. This contract change order covers the additional cost and contract time to complete the necessary work related to these unforeseen conditions. Sufficient funding is already in place for the additional work through the adopted capital improvement budget.


BACKGROUND

On April 21, 2022 a Contract was awarded in the amount of $1,578,078.00 to Emmetts Excavation, Inc., for the Sewer Rehabilitation in the area bound by Blackstone, Maroa, McKinley and Clinton Avenues.

This project consists of closed-circuit television (CCTV) video inspection and cleaning of the existing mains prior to the trenchless insertion of...