REPORT TO THE CITY COUNCIL
FROM: NICHOLAS D. MASCIA, PE, Assistant City Manager
Interim Director, Capital Projects Department
PAUL AMICO, PE, Director
Department of Public Utilities
BY: CASSIE L. SCHOLZ, PE, Assistant Director
Capital Projects Department, Utilities Project Management Division
CHARLES MASTERS, Engineer II
Capital Projects Department, Utilities Project Management Division
SUBJECT
Title
Approve Contract Change Order No. 2 with Floyd Johnston Construction Co., Inc., in the amount of $1,669,659.62, increasing the total not to exceed of $6,883,047.62, with ninety-two (92) additional calendar days for Leaky Acres Groundwater Recharge Facility Improvement Project (Bid File 12601278) (Council District 4)
Body
RECOMMENDATION
Staff recommends the City Council approve Contract Change Order No. 2 with Floyd Johnston Construction Co., Inc. in the amount of $1,669,659.62 with ninety-two (92) additional calendar days for the Leaky Acres Groundwater Recharge Facility Improvement Project (Project), and authorize the Capital Projects Department Director or designee to sign Contract Change Order No. 2 on behalf of the City of Fresno.
EXECUTIVE SUMMARY
On April 23, 2026, a Construction Contract was awarded in the amount $5,213,388.00 to Floyd Johnston Construction Co., Inc., for the Project to increase operational efficiency of the Leaky Acres Groundwater Recharge Facility (Facility). Due to receipt of additional State of California Department of Water Resources (DWR) Urban Community Drought Relief Grant funds for the Project, the Capital Projects Department seeks approval of Contract Change Order No. 2. This includes four (4) additive alternates for a total increase of $1,669,659.62 and time extension of 92 calendar days, for a revised contract total of $6,883,047.62 and 197 total calendar days.
BACKGROUND
On April 23, 2026, a Construction Contract was awarded in the amount $5,213,388.00 to Floyd Johnston Construction Co., Inc...