REPORT TO THE CITY COUNCIL
November 14, 2019
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
THROUGH: ANDREW J. BENELLI, PE, City Engineer/Assistant Director
Public Works Department, Traffic Operations and Planning Division
BY: RANDY GUILL, Supervising Engineering Technician
Public Works Department, Traffic Operations and Planning Division
SUBJECT
Title
RESOLUTION - Approving the Final Map of Tract No. 6191 and accepting dedicated public uses offered therein except for dedications offered subject to City acceptance of developer installed required improvements - East Fancher Creek Drive, West of North Armstrong Avenue (Council District 5)
Body
RECOMMENDATION
Staff recommends the City Council adopt a resolution approving the Final Map of Tract No. 6191 and accepting the dedicated public uses offered therein, to authorize the Public Works Director or his designee to execute the subdivision agreement on behalf of the City.
EXECUTIVE SUMMARY
The Subdivider, BN 5499 LP, INC., a California Limited Partnership (John A. Bonadelle, President), has filed for approval, the Final Map of Tract No. 6191, of Vesting Tentative Map No. 6191, for a 125-lot single-family residential subdivision with twenty outlots, located on the East Fancher Creek Drive, West of North Armstrong Avenue on 17.81 acres.
BACKGROUND
The Fresno City Planning Commission on April 17, 2019, adopted Resolution No. 13580 approving Vesting Tentative Map No. 6191 (Tentative Map) for a 125-lot single-family residential subdivision with twenty outlots on 17.81 acres. The Tentative Map was approved consistent with the Fresno General Plan to comply with the provisions of the Subdivision Map Act. The Final Map is technically correct and conforms to the approved Tentative Map, the Subdivision Map Act and the Fresno Municipal Code. The provisions of Section 66474.1 of the Subdivision Map Act require a final map that is in substantial compliance with the approved tentative map to be approved by the City Council.
The Subdivider has satisfied all other conditions of approval by executing the Subdivision Agreement for Tract No. 6191, submitted securities in the total amount of $3,885,000.00 to guarantee the completion and acceptance of the public improvements and $2,044,500.00 for a payment security and has paid the miscellaneous and development impact fees due as a condition of approval for the Final Map in the amount of $585,659.96. Covenants have been executed to defer eligible development impact fees totaling $1,585,109.16 to the time of issuance of building permit and final occupancy of each unit, for annual CFD-11 assessment notification, for maintenance of landscape improvements, for Fowler Interim Fee Surety, for special solid waste disposal services. The City Attorney’s Office has approved all documents as to form and the Risk Management Division has approved all security bonds and insurance certificates.
Maintenance District: A condition of approval of the Tentative Map is to maintain all landscaped areas, irrigation systems, trees and hardscaping located in public easements and outlots, all above ground infrastructure, such as concrete curbs and gutters, valley gutters, traffic control islands, medians, sidewalks and curb ramps, street name signage, street lighting and local street paving within and adjacent to the Final Map. The Final Map will share costs for all services in common with all final maps annexed to the Community Facilities District No. 11 (CFD-11) within the Tentative Map. The Subdivider has satisfied the maintenance requirement by annexing the subdivision into the City’s CFD-11 on November 7, 2019.
The Subdivider has executed the covenant for Maintenance of Certain Improvements and as a condition of the Subdivision Agreement, is required to provide every prospective purchaser of each lot of the subdivision the “Notice of Special Tax”, in accordance with the provision of Section 53341.5 of the California Government Code. The maximum annual assessment is $123.50 per lot with an annual 3% adjustment plus the increase, if any, in the construction cost index for the San Francisco Region.
ENVIRONMENTAL FINDINGS
Pursuant to CEQA Guidelines Section 15268(b)(3), approval of final subdivision maps is a ministerial action and is exempt from the requirements of CEQA.
LOCAL PREFERENCE
Local preference was not considered because this resolution does not include a bid or award of a construction or services contract.
FISCAL IMPACT
The Final Map is located in Council District 5. There will be no impact to the City’s General Fund. Approval by the Council will result in timely deliverance of the review and processing of the Final Map as is reasonably expected by the Subdivider. Prudent financial management is demonstrated by the expeditious completion of this Final Map inasmuch as the Subdivider has paid the City a fee for the processing of this Final Map and that fee is, in turn, funding the respective operations of the Public Works Department.
Attachments:
Resolution
Final Map of Tract No. 6191