REPORT TO THE CITY COUNCIL
November 19, 2020
FROM: SCOTT L. MOZIER, PE, Director
Public Works Department
THROUGH: RANDALL W. MORRISON, PE, Assistant Director
Public Works Department, Engineering Division
BY: JOHN STANBOULIAN, Public Works Manager
Public Works Department, Traffic Operations Center
SUBJECT
Title
Actions pertaining to Ventura Street-Kings Canyon Road Corridor Intelligent Transportation System (ITS) Adaptive Project (from Van Ness to Chestnut Avenues) - Bid File No. 3767 (Council Districts 3, 5 and 7)
1. Adopt a finding of Categorical Exemption per staff's determination, pursuant to Section 15301(c) Class 1 of the California Environmental Quality Act Guidelines (CEQA)
2. ***RESOLUTION - 45th Amendment to the Annual Appropriation Resolution No. 2020-159 appropriating $382,000 for the Ventura Street-Kings Canyon Road Corridor Intelligent Transportation System (ITS) Adaptive Project (Requires 5 affirmative votes) (Subject to Mayor's veto)
3. Award a construction contract in the amount of $1,578,972 to Audeamus Inc., dba Sebastian of Fresno, CA, as the lowest responsive and responsible bidder for the Ventura Street-Kings Canyon Road Corridor ITS Adaptive Project (from Van Ness to Chestnut Avenues)
Body
RECOMMENDATIONS
Staff recommends that City Council (1) adopt a finding of Categorical Exemption per staff determination, pursuant to Section 15301(c) Class 1 of the CEQA Guidelines, (2) adopt the 45th Amendment to the Annual Appropriation Resolution (AAR) No. 2020-159, (3) award a construction contract with Audeamus Inc., dba Sebastian, of Fresno, CA, in the amount of $1,578,972 as the lowest responsive and responsible bidder for the base bid, and authorize the Public Works Director or Designee to sign a standardized contract on behalf of the City.
EXECUTIVE SUMMARY
The Ventura Street-Kings Canyon Road corridor is a heavily traveled corridor in Fresno, connecting businesses, hospitals, and residences with downtown Fresno and State...