File #: ID18-0337    Version: 1 Name:
Type: Action Item Status: Passed
File created: 2/27/2018 In control: City Council
On agenda: 3/22/2018 Final action: 3/22/2018
Title: Annual update of the Traffic Operations and Planning Division lists for new traffic signal installations and traffic signal left turn phasing modifications.
Sponsors: Public Works Department
Attachments: 1. 18-0337 Attachment A - 2018 signal list 030418.pdf, 2. 18-0337 Attachment B - 2018 Left Turn Phasing List.pdf

REPORT TO THE CITY COUNCIL

 

 

March 22, 2018

 

 

FROM:                     SCOTT L. MOZIER, PE, Director

Public Works Department

 

BY:                                          ANDREW J. BENELLI, PE, City Engineer / Assistant Director

                                          Public Works Department

 

JILL GORMLEY, TE, City Traffic Engineer / Public Works Manager

                                          Public Works Department, Traffic Operations and Planning Division

 

 

SUBJECT

Title

 

Annual update of the Traffic Operations and Planning Division lists for new traffic signal installations and traffic signal left turn phasing modifications.

 

Body

RECOMMENDATIONS

 

Staff recommends that the Council receive the updated Annual Citywide Traffic Operations and Planning Division lists for proposed new traffic signal installations and traffic signal left turn phasing modifications.

 

EXECUTIVE SUMMARY

 

Staff has completed the annual update of Citywide Traffic Operations and Planning Division lists for proposed new traffic signal installations and left turn phasing installations. The update of these lists includes new traffic counts, analysis of accidents during the past year, traffic signals which have gone into construction during the past year and engineering consideration of other field changes such as new schools that have opened in the vicinity of the subject intersections. The scoring criteria are based upon traffic engineering criteria established by the Federal Highway Administration (FHWA) and the California Department of Transportation.

 

BACKGROUND

 

Every year, the Traffic Operations and Planning Division in Public Works conducts updated traffic counts, reviews intersection accident reports and performs an engineering analysis in accordance with adopted standards of the FHWA and California Department of Transportation. This analysis includes eight-hour traffic volumes, peak hour volumes, pedestrian counts, accident history and proximity of schools to the intersections.  Unsignalized intersections are analyzed to determine if installation of a traffic signal is warranted.  Warrants are evaluated purely using the Administration standards from the Manual on Uniform Traffic Control Devices. Existing signalized intersections that do not have left turn phasing (i.e., protected left turn movements via green arrows) are analyzed to determine if the installation of left turn phasing should be considered, which is based upon the number of peak hour conflicts between through traffic and opposing left turning vehicles or the number of accidents that would be correctable with installation of left turn phasing.

 

Intersections where new signal warrants are met, or where left turn phasing is recommended for consideration, are then objectively scored and ranked in order Citywide. The point system for new traffic signal installations conforms to the FHWA’s requirements and is based upon overall traffic volumes for both directions (10 points maximum), peak hour traffic (10 points maximum), three-year history for correctable accidents (5 points per correctable reported collision in the annual average), schools within 0.25 miles (10 points maximum), activity centers within 1,000 feet (3 points maximum), potential signal coordination benefits (5 points maximum), intersection sight distance (2 points maximum), funding opportunities or cost/benefit ratio (2 points maximum) and engineering judgment of special conditions (3 points maximum). The point system for left turn phasing installations is based upon the peak hour product of left turning vehicles and opposing through traffic (5 points maximum), three-year history for correctable accidents (5 points per correctable reported collision in the annual average), schools within 0.25 miles (10 points maximum), activity centers within 1,000 feet (3 points maximum), intersection sight distance (2 points maximum), funding opportunities or cost/benefit ratio (2 points maximum) and engineering judgment of special conditions (3 points maximum).

 

The updated City-wide Traffic Operations and Planning Division lists are included as Attachments “A” and “B”.  The lists also indicate the funding status of each intersection. Some intersections must be signalized as a condition of approval for a specific development and have been noted as “Developer to Install”.  Other intersections have been funded as capital improvement projects based upon scores in prior years and/or a successful grant application for state and federal funds.

 

Intersections that have been completed or that have started construction since the 2017 annual report have been removed from the ranking lists. It should be noted that this past year since the last update, one existing signalized intersection was upgraded with left turn phasing and four intersections were signalized. These intersections have been removed from the ranking worksheets. The ranking lists will be used to prepare the FY18 capital improvement budget and to apply for grants in an objective manner based upon available and projected traffic signal mitigation impact fees.  Council approved an update of the impact fees and the intersections covered by those fees on December 8, 2016.  Attached to this report, are the ranking lists for new signal installations, modifications for left turn phasing, and traffic flow improvements.

 

Funding for traffic signals in areas where new development is occurring is generated by the Traffic Signal Mitigation Impact Fee.  The fee program revenues were very high in 2006 and 2007, but declined significantly during the recession.

Previous fiscal year monthly averages are as follows:

 

Budget Year

Monthly Revenue

 

 

FY18

$145,861

FY17

$120,523

FY16

$89,773

FY15

$93,607

FY14

$81,356

FY13

$95,243

FY12

$60,009

FY11

$75,707

FY10

$63,885

FY09

$95,572

FY08

$124,223

FY07

$247,024

FY06

$258,020

 

                     

 

As compared to FY06 and FY07, there are currently a larger proportion of new developments which have construction requirements in excess of their fee obligation, which as a result of the City’s construction fee credit policy yields a more limited amount of impact fee revenue. Given the limited impact fees currently available for capital projects, the Department’s goal has been to pursue alternative funding sources such as federal and state grants for delivery of these projects. Impact fee revenue is also utilized to reimburse developers who have installed traffic signal improvements in excess of their fee obligation amount. Currently the traffic signal fee program owes approximately $670,000 to developers for previously completed traffic signal improvements.

 

ENVIRONMENTAL FINDINGS

 

By the definition in the California Environmental Quality Act (CEQA) Guidelines Section 15378, the update of the Traffic Operations and Planning Division lists does not qualify as a “project” as defined CEQA.

 

LOCAL PREFERENCE

 

Local preference was not implemented because the update of the lists does not include a bid or award a construction or services contract.

 

FISCAL IMPACT

 

The annual update of traffic signal ranking lists has been accomplished within the operating budget of the Public Works Department. There will be no additional impact on the General Fund.

 

Attachments:

 

“A” - 2018 Warranted New Traffic Signal Locations

“B” - 2018 Left Turn Signal Phasing Locations for Consideration